LEE, Mass. — The Massachusetts Department of Transportation (MassDOT) announced that crews will be conducting overnight paving operations and bridge and guardrail repair work on I-90 eastbound and westbound in Montgomery, Russell, Becket, Lee, and Blandford. 
 
The scheduled work will require some lane and shoulder closures, and is scheduled to take place as follows:
 
Lee/Becket
Pavement milling operations will be conducted nightly on I-90 westbound from mile marker 14 to mile marker 22, from Monday, June 5, to Friday, June 9, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning.  All work is anticipated to conclude by 5:00 a.m. on Friday, June 9.
 
Pavement milling operations will be conducted nightly on I-90 eastbound from mile marker 13.5 to mile marker 16, from Monday, June 5, to Friday, June 9, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning.  All work is anticipated to conclude by 5:00 a.m. on Friday, June 9.
  
Lee  
Guardrail repair operations will be conducted nightly on I-90 eastbound and westbound from mile marker 10.5 to mile marker 14.0, from Monday, June 5, to Friday, June 9, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning.  All work is anticipated to conclude by 5:00 a.m. on Friday, June 9.
 
Blandford/Becket
Guardrail repair operations will be conducted on I-90 eastbound and westbound from mile marker 20.0 to mile marker 33.5, on Sunday, June 4, and on Monday, June 5, during overnight hours from 8:00 p.m. to 4:00 a.m. the following morning. All work is anticipated to conclude by 4:00 a.m. on Tuesday, June 6.
 
Montgomery/Russell
Bridge repair work will be conducted nightly on I-90 eastbound and westbound at mile marker 36.0 from Sunday, June 4, to Friday, June 9, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning.  All work is anticipated to conclude by 5:00 a.m. on Friday, June 9.
 
Traffic will be allowed through the work zones. 
 
The work will require temporary lane closures to allow crews to safely conduct the paving, and bridge and guardrail repair operations.
 
Drivers who are traveling through the affected areas should expect delays, reduce speed, and use caution. 
 
All scheduled work is weather dependent and subject to change without notice.