South County Paving, Bridge, Guardrail, and Drainage Operations08:20AM / Monday, July 24, 2023 | |
LEE, Mass. — The Massachusetts Department of Transportation (MassDOT) crews will be conducting overnight and daytime paving operations and bridge, guardrail, and drainage repair work on I-90 eastbound and westbound in Montgomery, Russell, Lee, Becket, and West Stockbridge.
The scheduled work will require some lane and shoulder closures, and is scheduled to take place as follows:
Montgomery/Russell
Bridge repair work will be conducted nightly on I-90 eastbound and westbound at mile marker 36.0 from Sunday, July 23, to Friday, morning July 28, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning. All work is anticipated to conclude by 5:00 a.m. on Friday, July 28.
Lee/Becket
Paving operations will be conducted nightly on I-90 eastbound from mile marker 14.0 to mile marker 21.8, from Monday, July 24, to Friday, July 28, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning. All work is anticipated to conclude by 5:00 a.m. on Friday, July 28.
Lee
Guardrail repair operations will be conducted nightly on I-90 eastbound and westbound from mile marker 9.3 to mile marker 10.3, from Monday, July 24, to Friday morning, July 28, during overnight hours from 7:00 p.m. to 5:00 a.m. the following morning. All work is anticipated to conclude by 5:00 a.m. on Friday, July 28.
West Stockbridge
Drainage repair operations will be conducted daily at I-90 eastbound from mile marker 1.0 to mile marker 6.0, on Wednesday, July 26 and Thursday, July 27 during daytime hours from 7:00 a.m. to 5:00 p.m.
Traffic will be allowed through the work zones.
The work will require temporary lane closures to allow crews to safely conduct the paving, bridge and guardrail repair operations.
Drivers who are traveling through the affected areas should expect delays, reduce speed, and use caution.
All scheduled work is weather dependent and subject to change without notice.
|