MEMBER SIGN IN
Not a member? Become one today!
         iBerkshires     Southern Berkshire Chamber     Lee Chamber     Lenox Chamber     Berkshire Community College    
Search
MassDOT: South County Nighttime Road Work
10:42AM / Tuesday, September 10, 2024
Print | Email  

STOCKBRIDGE, Mass. — The Massachusetts Department of Transportation (MassDOT) is announcing that crews will be performing nighttime paving, guardrail, and bridge repair operations along I-90 eastbound and westbound from Monday night, Sept. 9, through Thursday night, Sept. 12, in Otis, Blandford, Stockbridge, West Stockbridge, and Becket.
 
Lane closures will be in effect, and traffic will be allowed through the work zones. The schedule for the work and lane closures is as follows:
 
Otis/Blandford
Paving operations will be conducted on I-90 eastbound from mile marker 21.0 to 25.0, Monday night, Sept. 9, through Thursday night, Sept. 12, starting each night at 6:00 p.m. and ending the next day by 6:00 a.m., with work concluding on Friday morning, Sept. 13.
 
Bridge work will be conducted on I-90 eastbound and westbound at mile marker 22.5, Monday night, Sept. 9, through Thursday night, Sept. 12, from 7:00 p.m. each night to the next day at 5:00 a.m.,  with work concluding by 5:00 a.m. on Friday morning, Sept. 13.
 
Stockbridge/West Stockbridge
Guardrail and bridge repair work will be conducted on I-90 eastbound and westbound from mile marker 3.0 to 6.5, Monday night, Sept. 9, through Thursday night, Sept. 12, from 7:00 p.m. each night to the next day at 5:00 a.m., with work concluding by 5:00 a.m. on Friday morning, Sept. 13.
 
Bridge repair work will take place on I-90 eastbound at mile marker 6.4, from Wednesday night, Sept. 11, through Thursday night, Sept. 12, from 7:00 p.m. each night to the next day at 5:00 a.m., with work concluding by 5:00 a.m. on Friday morning, Sept. 13.
 
Becket
Bridge repair work will be conducted on I-90 westbound at mile marker 18.4, Monday night, Sept. 9, through Thursday night, Sept. 12, from 7:00 p.m. each night to the next day at 5:00 a.m., with work concluding by 5:00 a.m. on Friday morning, Sept. 13.
 
Bridge repair work will be conducted on I-90 eastbound at mile marker 18.4, Monday night, Sept. 9, through Tuesday night, Sept. 10, from 7:00 p.m. each night to the next day at 5:00 a.m., with work concluding by 5:00 a.m. on Wednesday morning, Sept. 11.
 
Appropriate signage, law enforcement details, and messaging will be in place to guide drivers through the work area.
 
Drivers traveling through the affected areas should expect delays, reduce speed, and use caution.
 
All scheduled work is weather dependent and subject to change without notice.
0Comments
More Featured Stories
SouthBerkshires.com is owned and operated by: Boxcar Media 102 Main Sreet, North Adams, MA 01247 -- T. 413-663-3384
© 2024 Boxcar Media LLC - All rights reserved